MMQS

Detail Project

Heineken Line Extension

Project Details

Project Overview

Heineken Line Extension

4000sqm was added to accomodate a new returnable-line as well as a new keg-line. Pressure on the program due to new product launches and marketing agendas required a sectional completion of the building for the new line to be installed, commisioned and put into prouction. Further to the new production side this project also includes the last portion of consolidated facilities that will allow the demolition of the old engineering building to be actioned and the final step of the construction of the new 4000sqm Pack warehouse. This project was completed in mid-2018.

Project Images

Get in touch with us to discuss your next design project.

Scroll to Top