Project Details
- Client:
- Project Location:
- Project Value :
- Commencement Year:
- Transnet Capital Projects
- Durban
- R13 Billion
- 2013
TM1 – Coastal NMPP Terminal
Terminal 1, located at the Port in Durban in the Cutler Complex at Island View, is comprised of accumulator tanks to accommodate the various fuel products that will be transported by the NMPP pipeline. The terminal will have full metering and proving capabilities to receive fuel products from the various fuel companies based in Durban.
A new sophisticated control building as well as mainline and booster pumps, laboratory facilities and effluent control and spill basin are provided for as part of the Terminal 1 scope. Three mainline pumps have been installed which operate in parallel ensuring that the minimum number of pumps provide the required flow rate.
As the product demand increases, the number of parallel pumps can be increased as required. Construction is in accordance with a strict
Environmental Management Plan with onsite water treatment facilities to deal with any contaminated ground water that may be experienced.